Recent project references include the Sheringham Shoal Offshore Wind Farm where we managed and executed the Infield Array Cabling termination contract on behalf of our client Visser & Smit Marine Contracting (VSMC).
Hang Off Assembly | Cable Containment | Termination Preparation | Completed Termination |
This involved production of all offshore installation and testing procedures, project management and delivery of the full termination package. Deliverables included installation of 164 Hang Off Clamps, design and construction all Cable Containment, completion of 492 High Voltage (33kV) Switchgear Terminations using Euromold 440TB Series Separable ‘Tee’ Connectors and 3936 Single Mode Fibre Optic Fusion Spliced Terminations.
We also provided all post installation testing services including TDR, OTDR, IR & CR, Field Engineering Support, QA/QC and supervision of Mechanical Completion.